Inside David's Residence: A Construction Diary

Tify Homes Admin·16 August 2026·3 min read

Most buyers only ever see a construction project twice: the render before it starts, and the finished lobby after handover. Everything in between is a black box. We're trying to change that with David's Residence, so here's an honest look at where things actually stand.

Where we started

The Obasa Estate plot in Oba Akran, Ikeja sat as cleared land for the first few weeks of the project — not exciting to look at, but this is where a lot of the risk in a build actually gets resolved. Soil testing, drainage planning, and boundary survey all happen before a single block goes up, and getting them wrong is far more expensive to fix later than it is to get right now.

Foundation work

Foundation is the milestone most buyers underestimate. It's slow, it's mostly underground, and from the road it barely looks like progress — but it's the single most consequential phase of the build. Get the foundation wrong and everything above it inherits the problem.

Our target for this stage was 20% overall completion, covering:

  • Site clearing and setting out
  • Foundation trenching and casting
  • Damp-proofing and backfill

What "structural frame" actually means

Once the foundation cures, the frame goes up — columns, beams, and floor slabs, floor by floor. This is the stage where a project starts to look like a building for the first time, and it's also the stage our live tracker gets the most visits, because it's genuinely satisfying to watch a floor plate appear where there was nothing a month before.

MilestoneTarget %What it covers
Site Clearing & Setting Out5%Survey, clearing, boundary marking
Foundation20%Trenching, casting, damp-proofing
Structural Frame (Ground – 3rd Floor)45%Columns, beams, slabs
Roofing60%Roof structure and covering
Blockwork & Plastering75%Walls, external and internal finishing prep
Finishing90%Fittings, electrical, plumbing

Why we post updates instead of just a percentage

A number going up is reassuring, but it isn't proof. That's why every update on the construction tracker comes with a written note — what changed, and why — rather than a bar quietly moving. If a milestone slips, you'll see that here too, not just the milestones that go smoothly.

We'll keep adding to this diary as the build progresses. If you're currently deciding whether to book an inspection, the site is genuinely worth seeing in person at this stage — there's a very different feeling standing on a foundation slab than looking at a render of one.